Culzean - EIT hook-up and commissioning

Customer: Maersk Oil North Sea UK LimitedLocation: UK North Sea
Period: 2017-2019

Semco Maritime is participating in the EIT hook-up and commissioning (HUC) onshore preparation and offshore HUC execution of the new Maersk Oil UK gas field. The Culzean field is the largest North Sea gas field discovered in the past decade.
.

Competences and systems
  • Onshore preparation
  • Technical query resolution
  • Change management
  • Preparation of hook-up commissioning procedure
  • Interactive planning
  • EIT supervision
  • EIT manpower
  • Equipment and tool support
Highlights
  • Offshore work carried out from the Aberdeen base, involving approximately 200 employees from Semco Maritime for 8-9 months