Telecom solution for DanTysk
Customer: VattenfallLocation: The German North SeaPeriod: 2014-2015
Delivery and installation of SemTetra main equipment and active repeater solution on the DanTysk offshore wind farm consisting of 80 wind turbines. The installation of equipment was a combination of onshore and offshore tasks.
Competences and systems
- Line of sight
- TETRA
- VHF FM/AM
- UPS
- Project management
- Rope access
- Preparation of documentation
- Commissioning
- Fabrication
Highlights
- Fully redundant line of sight - distance approx. 90 km
- Full indoor TETRA coverage in all 80 turbines
- Early communication (system was delivered offshore prior to offshore substation (OSS) installation phase)
- The project was completed without any lost-time incidents (LTIs)
- Positive feedback from the customer