Cases

Gode Wind 1 & 2 - telecom

Written by Semco Maritime | Oct 3, 2015 10:00:00 PM

Telecom solution for Gode Wind 1 & 2

Customer: ØrstedLocation: The German part of the North SeaPeriod: 2013-2015


Telecommunication package for the Gode Wind 1 and 2 onshore and offshore wind farms.
The scope of supply under this project included EPCI, design configuration, testing and commissioning of the full telecom package.

Competences and systems
  • TETRA system
  • VHF FM/AM radio systems
  • Line-of-sight (LOS) system
  • Heli-light/MET control and hand terminals
  • Voice gateway
  • UPS
  • Project management
  • Documentation
Highlights
  • Turnkey delivery
  • Early communication system delivered offshore prior to offshore substation (OSS) installation phase
  • Redundant LOS and TETRA systems