Hejre Micro welding & MGP Installation – Rope Access

Customer: ØrstedLocation: Hejre in the Danish part of the North Sea
Period: 2015 - 2016

A comprehensive scope involved Semco Maritime rope access technicians at various stages of the project, including micro welding of strain gauges, installation of Marine Growth Prevention (MGP) rings and various other rope access scopes.

Competences and systems
  • Multi-skilled IRATA rope access team
  • Micro welding
  • Rigging
Highlights
  • Highly complex welding scopes and installations
  • Splash zone work and complex rope rigging to enable access in 3-dimensional aspects