A full electrical engineering, procurement, construction and installation (EPCI) of the substation for the Northwester 2 offshore wind farm.
The project involves all electrical disciplines including low-, medium- and high-voltage systems. 15 months from contract to sail off.
In reality, it was 16 months from contract signing to completing - still pretty fast!
The Northwester 2 was the third time we (together with Bladt Industries and ISC) delivered a complete substation to the developer Parkwind. In 2013, the Northwind substation was delivered and only three years later, Bligh Bank - both projects as EPCI contracts. The wind farm is installed about 46 km off the Belgian coast with a total installed capacity of 219 MW.