Customer: Seajacks
End Customer: SiemensLocation: Esbjerg, Denmark
Period: 2016


The project scope consisted of fabrication and sea fastening of blade rack structure and tower grillage with adapters ahead of Scylla’s work at the Veja Mate offshore wind farm. The sea fastening installed during mobilisation is used for three types of wind turbine generators (WTGs).

Competences and systems
  • Procurement
  • Painting
  • Modification
  • Upgrade
  • Nacelle grillage
  • Access stair tower for blade rack substructure
  • Transition piece (TP) gangway
Highlights
  • Complete project delivered on time
  • Costumer was very satisfied with Semco Maritime’s solution and performance