Telecom solution for Walney 1 & 2
Customer: ØrstedLocation: The UK part of the North Sea
Period: 2012
Delivery and installation of SemTetra main equipment and active repeater solution on the Walney 1 and 2 offshore wind farms consisting of 102 wind turbines. The installation of equipment was a combined onshore and offshore task.
Competences and systems
- Line of sight (LOS)
- TETRA
- VHF FM/AM
- Commissioning
- Fabrication
- Project management
- Document preparation
Highlights
- Early communication (system was delivered offshore prior to offshore substation (OSS) installation phase)
- Coordination of resources and project phases between the two assets
- The project was completed without any lost-time incidents (LTIs)