Reception Dina IMG_02662 HSEQ burgermenu Sustainability burgermenu2 Innovation burgermenu Cases burgermenu Latest news Buregermenu Press Buregermenu Contact burgermenu

General enquiries
Tel. +45 7916 6666
semco@semcomaritime.com

 

Semco Maritime
Esbjerg Brygge 30
DK- 6700 Esbjerg

semco-brand-graphic
A dry dock for the largest jack-ups

Dry docking of CJ70–X150-ST CAT-J

At Hanøytangen you find one of Europe’s largest dry dock facilities. Numerous semisubmersible drilling rigs has been dry-docked here throughout the years. However, for many years, the docking of jack-ups remained a problem due to the rocky seabed north of Stavanger ...

Download e-book about the dry-docking of CJ70–X150 rigs...

West Elara dry-docked

Hanøytangen is the only coastal location north of Stavanger suitable for accommodating large jack-up rigs and jacking them out of the water ...

Read on - or download e-book below -  to see how we reinforced the dock bottom to be able to dry-dock the impressive GustoMSC CJ70-X150 and the CJ70-X150-ST CAT-J rigs.

 

Ultra-harsh environment drilling jack-ups

Over the years, we had been investigating ways of accommodating jack-ups at Hanøytangen, but with limited success. Eventually, however, we managed to identify a rig type that might have the potential we were looking for, namely the ‘GustoMSC CJ70-X150 (and the even larger CJ70-X150 ST CAT-J) – ultra-harsh environment drilling jack-ups’.

This jack-up has one of the most popular and common rig designs used in the deeper part of the Norwegian North Sea and is one of the world’s largest, heaviest and tallest drilling rigs - having a combined weight of up to 40,000 tons and a leg length exceeding 200 metres. Eleven (11) jack-ups of this type have been constructed at various yards in the Far East and all of them are now working in the North Sea.

Design process and solution

How to prepare docking facilities

The rack plate of the CJ70-X150 extends 100 mm beyond the chord scales, i.e. only the rack plate will be in contact with the dock bottom.

The rack plate of GustoMSC CJ70-X150 extends 100 mm beyond the chord scales, i.e. only the rack plate will be in contact with the dock bottom.

Due to this leg design, we could see that the jack-up could be suitable for dry docking at Hanøytangen. All CJ70 design units have the same footprint with three rack areas of 1050 mm x 210 mm under each leg. The centre rack steel plate has a yield strength of 690 MPa.

We made some preliminary calculations of yield and buckling loads including typical weights of hull, leg and variable load. The calculations came out with the result that margins were satisfactory. Sliding and overturning calculations all proved a very low utilisation load and were found acceptable.

Our initial intention was to place the CJ70 directly on the bottom of the dry dock. However, having checked the capacity of the bedrock it was obvious that the bedrock would not be able to withstand the load from the rack plate. We therefore installed some steel plates of various thicknesses below the rack plates and calculated the effect.

However, the preparatory phase was much more difficult than expected. The pressure at the rack contact area exceeded 30,000 tons per m2. Even with steel plates up to a height of 1,600 mm, we had difficulties transferring the rack load into the bedrock. It proved to be almost impossible to obtain a satisfactory low pressure that would be tolerated by the bedrock.

Another issue was the high steel plinths for the CJ70, which would make it very difficult to perform a normal docking operation. We therefore decided to submerge the steel plinths into the bedrock. However, we still had difficulty spreading out the forces.
The solution was to cut a circular 1-metre hole in one of the upper plates and then force the pressure outwards. We also widened the lower plates to 3m x 3m followed by 2.5m x 2.5m plates and 2m x 2m plates. Finally top plates of 1m x 2m are installed.

A 400 mm strong reinforced concrete slab was casted to transfer the forces from the steel plinths and legs into the bedrock. A 1-metre thick reinforced concrete wall was casted around the plinths. The steel used for the plinths has a yield strength of 350 MPa except for the top plate, which has a value of 690 MPa. Subsequently, DNV-GL in Oslo evaluated and verified the conceptual design, and we received the final acceptance letter on September 20, 2017.

image4

Installation of steel plinths

As mentioned, all CJ70 design units have the same footprint, but the steel plinths must be installed very precisely in the footprint, both horizontally and vertically. Therefore, we have compiled a very detailed drawing (verified by third-party company) of the theoretical footprint.

We must be able to have a touchdown on all nine steel plinths at the exact same time. The maximum deviation from the theoretical footprint should not exceed 40 mm in the horizontal plane. The height differences of the steel plinths within one leg should not exceed 18 mm, as this would cause RPD (Rack Phase Difference) problems.

After installation of the steel plinths and before opening of the dock gate, two independent survey companies finally verified the footprint. We managed to install the steel plinths perfectly within the tolerances.

IMG_5689

In the photo above, steel plinths are being submerged for forward leg – note the red top plate.

image6

In the photo above, you see the dry dock after the nine steel plinths have been submerged in the dock bottom. The leg distance is 70 m.

Positioning of the GustoMSC CJ70-X150 into dry dock

It is needless to say that the rig must be installed precisely in order to be accepted for jacking up. A very detailed rig installation procedure has been prepared, and the warranty surveyor has issued a Certificate of Approval (CoA) stating that docking facilities meet regulatory, technical and safety requirements. The 690 MPa top steel plates have been painted in bright red and marked with chord and leg number in black. The rack plates of the rig legs must be in clear contact with the 1m x 2m steel top plate.

Installation phases:

  1. The first phase is when the rig arrives at Haughlandsosen. Here, three (3) harbour tugs and one (1) line boat will take over the rig from the anchor handling tugs (AHTs) used for sea carriage.

  2. The tugs will manoeuvre the CJ70 rig to the gateway of the dry dock where the line boat will pull the wires from the eight (8) winches - four (4) onshore winches and four (4) rig winches. The tow master, the offshore installation manager (OIM) and the warranty surveor will be responsible for towing the rig into the right position. Moreover, a mooring or dock master will be responsible for the winches. The mooring or dock master will refer to the tow master. Before entering the dry dock, the jack-up will be fitted with hi-tech positioning equipment including total laser stations and rotating prisms. Final tow-in can be followed via two (2) control systems with real time-monitoring screens onshore and on board the rig. 

  3. When the rig is assumed to be in the correct position, three (3) remotely operated vehicles (ROVs) will be launched on the orders of the tow master - one per leg. One of the ROVs is a spare vehicle. A radio link system used for the ROVs will allow the tow master, warranty surveyor and dock master to visually verify the position of the legs. All equipment used for tow-in is with double or triple backup.

Jacking up the rig

The warranty surveyor shall accept the position of the CJ70 rig when properly towed into place. The warranty surveyor can only ‘accept’ the position of the rig if all rack plates are in full contact with the red top plates. The rig is now ready for jack-up in accordance with the operation manual. No preload will be required.

Having jacked up the rig to an adequate air gap, the clamps can be installed and the cantilever skidded out. Optionally, the dock gate can be installed and the dry dock emptied. When the dock is emptied is it possible to repair the spud cans or do other subsea repairs or modifications. The position of the rig is chosen to give the starboard crane maximum coverage of the quay. Once skidded out, the cantilever will be in over the end of the dock and the BOP can be exchanged.

image8

The GustoMSC CJ70 – X150 in proposed position in the dry dock.

Download e-book

Dry-docking the CJ70 rigs

We have gathered the entire story about how we made our dry dock ready for this specific rig type in a handy e-book!

Contact us at Hanøytangen to learn more

Robert Thoft Christensen

Head of Projects, Rig and Marine

Semco Maritime AS
Hanøytangen 130
5310 Hauglandshella
Norway

Nikolaj Vejlgaard

Vice president, Rig projects

Semco Maritime A/S
Esbjerg Brygge 30
6700 Esbjerg
Denmark