Hornsea Project One, telecom
Customer: Bladt IndustriesEnd-customer: ØrstedLocation: The North Sea, UKPeriod: 2016-2018
Scope of work including detailed EPCI, integrated in-house system testing, installation supervision and commissioning of telecommunication systems on three offshore substations and one reactive compensation station (RCS)..
Competences and systems
- PA/GA
- PABX
- LAN/WAN data network
- Fibreoptics
- TMS
- CCTV
- AIS & ADS-B
- LOS
- TETRA
- VHF/AM & FM
- Identification systems
- Navigation aids
- Weather station
Highlights
- Construction and installation of three (3) offshore substations for the largest wind farm in the world (1,200 MW – 2018)
- All three (3) offshore substations were delivered on time