Customer: Bilfinger Marine & Offshore Systems
End Customer: Vattenfall
Location: Esbjerg, Denmark
Period: 2015
Construction and installation of 342 tons of sea fastening and handling equipment on board the installation vessel Pacific Orca. Construction was carried out at Semco Maritime´s facilities in Esbjerg whereas installation was made at the quayside. The sea fastening equipment was used for the installation of monopiles at the Sandbank wind farm.
Competences and systems
- Project management
- Installation on board vessel and fabrication acceptance test (FAT)
- Steel construction
- Installation of hydraulic systems
Highlights
- Positive feedback from customer
- Complete project delivered on time
- Completed without any lost-time incidents (LTIs) or safety issues
- Optimised the execution phase by maintaining a strong focus on efficiency and downtime