Rødsand 2
Offshore Substation

Customer: Bladt IndustriesEnd customer: EnerginetLocation: The Danish part of the North Sea Period: 2008 - 2010Topside weight: 1200 tonsCapacity: 207 MW


The scope included a full engineering, procurement, construction and installation (EPCI) contract for the offshore substation. The project consisted of several electrical disciplines including low-voltage systems.

Competences and systems
  • Low-voltage systems
  • Cableways and cable pulling
  • HVAC systems
  • Firefighting systems
  • Fire detection systems
  • Communication and IT systems
  • Diesel power
  • Project management
Highlights
  • Energinet´s first offshore wind farm
  • Placed on gravity foundation
  • Project delivered on time with positive feedback from customer